Tentative Work Schedule

September 6, 2023

 

Work in the NE section consists of Mowing Back Slopes on NE CR 225 and NE 216th St. 

 

Work in the NW section consists of Grading NW 41st Ave. and NW 44th Ave., Replacing 2 Culverts on NW 31st Ave. and Mowing NW CR 229 and NW CR 229A

 

Work in the SE section consists of Grading SE 31st St., SE 1st Ave. and SE 53rd St.

 

Work in the SW section consists of Grading SW 136th St., SW 144th and SW 168th St.

 

 

We will have 2 DOC (BCSO-JAIL) Officers and 3 Inmates Picking Up Trash on SE 21st Ave.