Tentative Work Schedule

January 8, 2020

 

Work in the NE section consists of Working on Clearing area for new road going in on NE 20th Ave.

 

Work in the NW section consists of Patching pot holes on NW CR 225

 

Work in the SE section consists of Grading SE 11th Ave.

 

Work in the SW section consists of Grading SW 104th Ave., SW 105th Ave. and SW 101st Ave., Picking up 3 mattresses on SW 163rd and Picking up 2 couches o SW 147th (Brooker pit road)

 

 

We received 3 DOC Squads for a total of 13 people.

 

1 Squad will be Picking up trash and Weed Eating SE 8th Ave. & SE CR 21B

 

1 Squad will be directing Traffic and assisting with Patching Pot Holes on NW CR 225

 

1 Squad will be assisting with cutting tops out of trees and cutting limbs where new road is going in on NE 20th Lane