Tentative Work Schedule

September 8, 2020

 

Work in the NW section consists of Grading NW 212th, 74th & NW 215th Way, Open up ditches on NW 71st Ave. and Trim ROW on NW 105th Ave.

 

Work in the SE section consists of Cleaning out concrete ditches on SE 55th Ave.

 

Work in the SW section consists of Mowing SW CR 231 (Dedan Loop) and SW CR 18

 

 

We received 2 DOC Squads for a total of 10 People

 

1 Squad will be Weed-eating whole ditch on NW 59th Loop

 

1 Squad will be Weed-eating whole ditch on SW 35th Street