Tentative Work Schedule

July 22, 2021

 

Work in the NE section consists of Grading NE 20th Lane, NE 247th and Carter Road, Mowing NE 216th St., NE 213th St., NE CR 225, NE 204th St., NE 20th Ln. and NE 24th Loop and Replacing a Gate that was damaged by one of our Mowers on NE 179th St.

 

Work in the NW section consists of Grading NW 41st, NW 211th, NW 53rd and NW 219th and Fixing Guardrail and a Crossover on NW CR 233

 

Work in the SE section consists of Patching a driveway on SE CR 230A and Patching Pot Holes on SE 30th St.

 

Work in the SW section consists of Patching a driveway on SW CR 237 and Mowing the SW 75th Ave. Collection site

 

 

We received 2 DOC (BCSO-JAIL) Squads and 6 Inmates

 

1 Squad will be Weed eating around the Guardrails and Bridge on SE CR 325

 

1 Squad will be Picking up trash on SW CR 227 then will be Picking up trash on SW CR 225