Tentative Work Schedule

September 28, 2021

 

Work in the NE section consists of Grading NE 5th Ave. and NE 20th Lane, Replacing 2 Crossover pipes on NE 17th Ave. and Mowing Starke Solid Waste Site

 

Work in the NW section consists of Grading NW 178th Loop and Mowing NW CR 229 Solid Waste Site

 

Work in the  SE section consists of Grading SE 73rd, SE 4th, SE 5th and SE 7th

 

Work in the SW section consists of Grading County part of SW 83rd Ave. and SW 120th Ave., Mowing ROW on SW 160th Ave. and Mowing SW 75th Ave. (Slab Road) Solid Waste Site

 

We will also be Mowing the Fire Department Sites

 

 

We received 2 DOC (BCSO-JAIL) Officers and a total of 5 Inmates

 

1 Squad and 3 Inmates will be assisting with Replacing Crossover pipes on NE 17th Ave.

 

1 Squad and 2 Inmates will be Picking up trash and Weed eating on SW CR 227