Tentative Work Schedule

September 25, 2023

 

Work in the NW section consists of Grading NW 219th St. and NW 257th St. and Mowing NW CW 235

 

Work in the SE section consists of Hauling 1/2 load of Concrete to SE 49th Ave. to patch a washout

 

Work in the SW section consist of Grading SW 163rd St., SW 82nd Ave. and SW 132nd Ave., Prepping SW 106th Ave. for Chip Sealing and Mowing SW CR 235 and SW 161st