Tentative Work Schedule

March 2, 2021

 

Work in the NE section consists of Digging out ditches and Opening up Culverts on NE 213th St.

 

Work in the NW section consists of Grading NW 212th & NW 80th, Add limerock to NW 247th St., Fix washout on NW 188th Ter., Cleaning out ditches and getting water to flow on NW 251st St., Mow NW CR 235 and Patch Pot Holes on NW 177th St.

 

Work in the SE section consists of Grading SE 38th and SE 46th Loop and Patching Pot Holes on SE 21st Ave.

 

Work in the SW section consists of Mowing SW CR 235

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be Picking up trash and weed eating SW CR 231

 

1 Squad will be Picking up trash and weed eating NW CR 235