Tentative Work Schedule

April 8, 2019

 

Work in the NW section consists of Zipping NW 219th St., Digging NW 53rd ditch, Grading NW 75th, NW 188th & NW 185th and Patching Pot Holes in Pleasant Grove area

 

Work in the SE section consists of Patching Pot Holes on SE 17th Ave.

 

Work in the SW section consists of Digging the ditch on SW CR 100A and Grading SW 101st Ave.

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be Picking up concrete near NW CR 229 ( Arthur Gaskins) then going to SE CR 18 ditch (Harvey Rhoden)

 

1 Squad will be Digging the ditch on SW CR 100A