Tentative Work Schedule

November 14, 2022

 

Work in the NW section consists of Grading NW 41st, NW 209th and NW 35th and Cleaning out Ditches on NW CR 235

 

Work in the SE section consists of Patching Pot Holes on SE 66th, Mowing ROW on SE 109th and Mowing SE 17th, SE 144th, SE 19th and SE 148th

 

Work in the SW section consists of Grading SW 64th, SW 65, SW 66th and SW 163rd

 

We will be Picking up Tree Debris all over the County

 

 

We received 1 DOC Officer (BCSO-JAIL) and no Inmates.  He will be filling in for the Maintenance Department