Work Schedule

 

 

Work in the NE section consists of Pulling ditches on 173rd St. and Picking up a chair on NE 6th Ave. and picking up a chair and trash on NE 213th

 

Work in the NW section consists of Grading and Picking up trash and chairs on 180th St. & 71st Ave.

 

Work in the SE section consists of Grading, Picking up couches and chairs on SE 144th (Old Asphalt plant), Pick up debris on SW CR 231 and Patch pot holes on SE CR 325

 

Work in the SW section consists of Grading, Mowing and Removing dirt and opening up pipe, Pick up debris and Patch pot holes

 

We will also be hauling 2 loads of sand to each of the following locations for Sand Bags: 

     City of Starke Purchasing Dept. (Orange Street)

     City of Lawtey

     Heilbronn Springs VFD

 

 

We received 2 DOC Squads for a total of 13 people

 

1 Squad will be working with Charles removing dirt & opening up pipe  on SW CR 18, Picking up debris and Patching pot holes

 

1 Squad will be weed eating around Bridges, Guardrails and Crossovers in NW section

 

1 Squad from the Transition House  (5 people) will be Patching a driveway on SE 66th St.