Work Schedule

 

Work in the NW section consists of Grading, Mowing and Patching culvert

 

Work in the SE section consists of Grading and Cutting up, Cleaning up, Chipping and Hauling off from Speedville Park and SE 8th Ave.

 

Work in the SW section consists of Cutting up, Cleaning up, Chipping and Hauling off and Patching washed out roads

 

 

We received 3 DOC Squads for a total of 19 people

 

1 Squad will be assisting in Cutting and Chipping in the SW section

 

1 Squad will be assisting in the Cutting up, Clean up and Chipping in the Speedville Park and SE 8th Ave. area

 

1 Squad will be Mowing, Weed eating in NW section ahead of mowers

 

 

1 Squad from the Transition House (3 people) will be assisting in patching culvert in NW section