Tentative Work Schedule

November 29, 2023

 

Work in the NW section consists of Grading NW 71st Ave., NW 205th, NW 203rd and NW 71st Pl., Patch Pot Holes on NW 200th St. and NW CR 235 and Add Limerock to NW 71st Ave.

 

Work in the SE section consists of Grading SE 50th St., Roads off SE CR 21B and SE 46th Loop, Patch Driveways on SE 21st Ave. and Mow Shoulders of the Road in Hampton Area and SE 21st Ave.

 

Work in the SW section consists of Grading SW 163rd St., SW 136th St. and SW 137th St. Patch Pot Holes on SW CR 235 and Mow SW CR 235 and SW CR 231

 

 

We received 2 DOC (BCSO-JAIL) Officers and 3 Inmates

 

1 Officer will be working in the Courthouse

 

1 Officer and 3 Inmates will will be Picking Up Trash and Weed Eating SE 21st Ave.