Tentative Work Schedule

February 27, 2024

 

Work in the NE section consists of Hauling Asphalt, Packing and Paving Utility Loop at the Fairgrounds

 

Work in the NW section consists of Grading NW 198th St. near SR 100 W (off of NW CR 235), Picking up debris and Mowing the Shoulders of the road on NW 38th Ave.

 

Work in the SE section consists of Grading SE 11th Ave.

 

 

We received 2 DOC (BCSO-JAIL) Officers and 4 Inmates

 

! Officer will be assisting in Maintenance

 

1 Officer and 4 Inmates will be picking up trash on NW CR 225