Tentative work Schedule

February 17, 2021

 

Work in the NE section consists of Cleaning out culverts on NE CR 225

 

Work in the NW section consists of Grading NW 41st Ave. & NW 44th Ave., Open up culverts on NW 196th St. and Add limerock to NW 40th St.

 

Work in the SE section consists of Grading SE 49th Ave. and Pick up tree debris and Clean out culverts on SE 21st Ave., SE 38th and SE 109th

 

Work in the SW section consists of Grading SW 132nd Ave. and Clean out ditch on SW CR 18

 

 

We received 2 DOC Squads for a total of 8 people

 

1 Squad will be Picking up trash and weed eating NW CR 125

 

1 Squad will be Picking up trash and weed eating SW CR 225