Tentative Work Schedule

June 22, 2023

 

Work in the NE section consists of Grading NE 213th St. and NE 20th Ave.

 

Work in the NW section consists of Grading NW 38th Ave. and Picking up Trash and Straighten Signs on NW CR 233

 

Work in the SE section consists of Spreading Limerock on SE 38th Ave. 

 

Work in the SW section consists of Grading SW 101st Ave., SW 83rd Ave. and SW 106th Ave. and Picking up Trash and Straighten Signs on SW CR 235

 

We will also be Picking up Tree Debris and Tires all over the County