Tentative Work Schedule

October 22, 2020

 

Work in the NW section consists of Prepping NW 214th St., Cutting & Trimming limbs, Keeping debris off of roadway and Mulching limbs on NW CR 225, Chipping limbs on NW CR 229 and Mowing ROW on NW 219th St. & NW 53rd Ave.

 

Work in the SE section consists of Mowing Keystone Landfill 

 

Work in the SW section consists of Grading SW 147th Ave., SW 120th Ave. and SW 163rd St.

 

 

We received 2 DOC Squads for a total of 8 people

 

1 Squad will assist with Chipping on NW CR 229

 

1 Squad will Weed Eat the ditch on SE 66th St. and Weed eat around Guardrails on SE 150th St. and then go assist with Chipping on NW CR 229