Tentative Work Schedule

September 24, 2019

 

Work in the NE section consists of Cleaning out ditches on NE 21st Ln. and Mowing NE 218th St.

 

Work in the NW section consists of Grading NW 71st, NW 85th, NW 84th, NW 82nd & NW 75th and Mowing NW 41st Ave.

 

Work in the SE section consists of Grading SE 45th and SE 21st Ave. and Mowing SE CR 221, SE CR 325, SE CR 18, SE CR 21B and SE 8th Ave.

 

Work in the SW section consists of Grading SW 104th, Patching Pot Holes and Driveways on SW CR 18 and Mowing around bridges on SW CR 237 and in SW section

 

 

We received 3 DOC Squads for a total of 11 people

 

1 Squad will be Trimming brush at the corner of SW CR 231 (Dedan Loop) and SW CR 18 (on the Brooker side)

 

1 Squad will be Patching Pot Holes and Driveways  on SW CR 18

 

1 Squad will be Cleaning out the ditches on NE 21st Lane