Work Schedule

 

Work in the NE section consists of Grading

 

Work in the NW section consists of Grading, Chipping, Mowing and Repairing wash outs

 

Work in the SE section consists of Grading, Chipping and Building a head wall

 

Work in the SW section consists  of Filling in and repairing washouts and washed out roads

 

 

We received 2 DOC Squads consisting of 13 people

 

1 Squad will be trimming, chipping and hauling off debris in the NW section

 

1 Squad will be trimming, chipping and hauling off debris in the SE section

 

1 Squad from the Transition House ( 3 people) will be building a head wall in the SE section