Work in the NW section consists of Grading off of NW CR 125, Trimming ROW on NW 188th St. and Digging the ditch on NW 251st 

 

Work in the SW section consists of Prepping SW 101st Ave. for Fog Sealing and Mowing SW CR 18, SW CR 225A and SW CR 227

 

 

We received 2 DOC Squads for a total of 11 people

 

1 Squad will be Picking up trash and Weed eating NW 84th Ave.

 

1 Squad will be Picking up trash and Weed eating NW CR 235

 

1 County Officer will be directing traffic for Digging Ditch on NW 251st