Tentative Work Schedule

May 28, 2019

 

Work in the NE section consists of Mowing with the Zero Turn on NE 19th Ave.

 

Work in the NW section consists of Installing a culvert on NW 71st Ave. between NW CR 233 and NW CR 229A and Mowing on NW CR 225

 

Work int eh SE section consists of Grading SE 11th Ave. and SE 46th Loop and Cleaning out the ditches on SE CR 325

 

Work in the SW section consists of Grading SW 64th Ave.

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be directing traffic on SE CR 325 for Cleaning out the ditches

 

1 Squad will be directing traffic for Installing a culvert on NW 71st Ave. between NW CR 233 and NW CR 229A then going to SE CR 325 to Clean out Ditches