Tentative Work Schedule

October 8, 2020

 

Work in the NE section consists of Mow ROW on NE 14th Ave. and NE 24th Loop

 

Work in the NW section consists of Grading NW 41st Ave., NW 209th and NW 35th Ave. and Cleaning out ditches on NW 188th

 

Work in the SE section consists of Grading SE136th Loop, SE 129th St. and SE 125th Ter.

 

Work in the SW section Grading, Patching troughs, Trimming Trees and Chipping on SW CR 235, Mowing SW CR 231 & SW CR 237 and Cleaning out ditches on SW 85th Lane 

 

 

We received 2 DOC Squads for a total of 8 people

 

1 Squad will be Picking up trash and Weed eating on NW 177th St.

 

1 Squad will be assisting with Patching troughs and Chipping on SW CR 235