Tentative Work Schedule

June 12, 2019

 

Work in the NE section consists of Repairing the road at the Crossover pipe on NE 15th Ave.

 

Work in the NW section consists of Grading NW 62nd, NW 251st, NW 267th and NW 84th

 

Work in the SE section consists of Grading SE 18th Way & Re Grading SE 17th Ave and Cleaning out th ditch on SE CR 325

 

Work in the SW section consists of Grading SW 101st, SW 163rd, SW 105th & SW 92nd and Trimming and Chipping on SW 75th Ave.

 

 

We received 3 DOC Squads for a total of 13 people

 

1 Squad will be Picking up trash and Weed eating on SW CR 225

 

1 Squad will be Picking up trash and Weed eating on SW CR 18

 

1 Squad will be directing traffic for repairing the road at the Crossover pipe on NE 15th Ave. and then going to NW 110th to Trim and Weed eat