Tentative Work Schedule

November 6, 2018

 

Work in the NE section consists of Pulling Ditches on NE 171st St. and Trimming and Chipping on NE 7th

 

Work in the NW section consists of Rocking NW 75th Ave. and Grading

 

Work in the SE section consists of Installing culverts on SE 20th Ave. & SE 66th St., Patching Driveways and Pot Holes on SE 66th St., Trimming and Chipping on SE 16th St. and Mowing SE 46th Loop with the Side Arm Mower

 

Work in the SW section consists of Zipping SW 101st Ave., Installing culverts on SW CR 227 and Mowing SW CR 235

 

 

We received 2 DOC Squads for a total of 11 people

 

1 Squad will be Trimming and Chipping on NE 7th 

 

1 Squad will be directing traffic on SW CR 227 for Installing a culvert