Tentative Work Schedule

March 20, 2024

 

Work in the NW section consists of Mowing the Shoulders of the Road on NW 41st Ave.

 

Work in the SE section consists of Grading SE 43rd Ave., SE 46th Ave. and SE 86th St.

 

Work in the SW section consists of Cleaning out the Ditches, Opening up the Culverts, Hauling, Spreading Limerock and Grading on SW 105th Ave.

 

 

We received 2 DOC (BCSO) Officers and 2 Inmates

 

1 Officer will be assisting in Maintenance

 

1 Officer and 2 Inmates will be Picking Up Trash on SW CR 18