Work Schedule

 

Work in the NE section consists of Patching driveways and Pot holes

 

Work in the NW section consists of Adding Enzymes and Packing a road, Scooping ditches, Installing a culvert and Chipping debris

 

Work in the SE section consists of Grading

 

Work in the SW section consists of Grading and Lime rocking and Pulling ditches and Packing a road

 

 

We received 2 DOC Squads for a total of 12 people

 

1 Squad will be Chipping in the NW

 

1 Squad will be directing traffic in the NW

 

 

! Squad from The Transition House (1 person) will be Patching driveways & pot holes in the NE & SE