Tentative Work Schedule

 

February 26, 2019

 

Work in the NW section consists of Grading NW 75th, NW 193rd, NW 188th & NW 185th, Installing culverts at NW CR 229 (behind Pleasant Grove Methodist  Church), 8883 NW CR 125 and Dig the Ditch on NW CR 235 (Nettle's Ditch) and Patch driveways on NW 71st

 

Work in the SW section consists of Grading SW 101st Ave., SW 155th St., Patch a driveway at 11150 SW 92nd St. and Patch troughs on SW CR 18 from Brooker to 301

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be Picking up trash and weed eating on SE CR 21B and SE 8th Ave.

 

1 Squad will be Picking up trash and weed eating on SW CR 18