Tentative Work Schedule

October 31, 2018

 

Work in the NW section consists of Pulling & limerocking NW 228th, Limerocking NW 75th Ave., Scoop ditches on NW 84th Ave., Dig the ditch on NW 53rd Ave., Patch the driveway at 6835 NW CR 233 and Mow NW CR 229 & NW CR 235

 

Work in the SE section consists of Trimming and Chipping limbs on SE 16th Way and SE 16th St., Mowing SE 50th, SE 51st, & SE 52nd with the Side Arm Mower and Patching pot holes on SE 48th

 

Work in the SW section consists of Zipping, Adding Clay and Enzymes to SW 101st Ave.

 

 

We received 3 DOC Squads for a total of 17 people

 

1 Squad will be patching pot holes on  SE 48th and a driveway at 6835 NW CR 233

 

1 Squad will be Trimming and Chipping limbs on SE 16th Way and SE 16th St

 

1 Squad will be directing traffic for Scooping ditches on NW 84th Ave.