Tentative Work Schedule

November 19, 2019

 

Work in the NW section consists of Digging ditches starting around 21541 NW CR 235 and Mowing NW 71st Ave.

 

Work in the SE section consists of Grading SE 11th Ave., Mowing SE 49th Ave., SE CR 221 & SE CR 325 and Patching a driveway at 15384 SE CR 230A

 

Work in the SW section consists of Grading SW 101st Ave., Picking up Concrete Barricades on SW 163rd St. and bring to BCRD Shop and Mowing SW CR 235 and SW 161st St.

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be Picking up trash and weed eating SE 49th Ave. from SE CR 18 and going South to the end of County Maintenance Sign then from SE CR 18 and go North behind school

 

1 Squad will be Picking up trash and weed eating on NW CR 235 starting around 21541 and going to SR 100

 

1 Squad will be directing traffic and assisting with digging ditches on NW CR 235 starting around 21541