Tentative Work Schedule

February 5, 2020

 

Work in the NW section consists of Cleaning out a ditch on NW CR 235 and on NW 122nd Pl and Patching Pot Holes on NW CR 225

 

Work in the SE section consists of Grading off of SE CR 18

 

Work in the SW section consists of Fog Sealing SW 101st Ave.

 

 

We received 3 DOC Squads for a total of 10 people

 

1 Squad will be Picking up trash and weed eating on SE CR 18

 

1 Squad will be Picking up trash and weed eating on SE CR 221

 

1 Squad will be directing traffic on SW  101st Ave and Blowing sand off of the road