Tentative Work Schedule

December 12, 2019

 

Work in the NE section consists of Grading NE 204th St. and NE 171st St. and Installing a Crossover pipe and clean out the the ditch on NE 6th Ave.

 

Work in the SE section consists of Grading SE 50th, SE 51st, SE 31st and SE 50th (off of SE CR 21B)

 

Work in the SW section consists of Shoulder work on SW CR 235, Mowing SW 101st Ave. and Filling in troughs on SW CR 227

 

 

We received 3 DOC Squads with a total of 14 people

 

1 Squad will be directing traffic for filling in troughs on SW CR 227

 

1 Squad will be directing traffic for Installing Crossover pipe and Cleaning out the ditch on NE 6th Ave.

 

1 Squad will be directing traffic  for doing Shoulder work on SW CR 235