Work Schedule

 

Work in the NE section consists of Grading

 

Work in the NW section consists of Milling a road, Mowing and Chipping limbs

 

Work in the SE section consists of Grading

 

Work in the SW section consists of Grading, Milling a road, Patching wash outs and Replacing blocks on Bridge Guardrail

 

 

We received 2 DOC Squads for a total of 7 people

 

1 Squad will assist in Chipping limbs in NW

 

1 Squad will pick up trash and weed eat in SE & NE

 

 

1 Squad from The Transition House (2 people) will be replacing blocks on Bridge Guardrail in SW