Tentative Work Schedule

March 5, 2020

 

Work in the NE section consists of Filling in and Patch troughs on NE 154th St.

 

Work in the NW section consists of Zipping and Propping NW 219th St. for Fog Sealing, Grading NW 62nd Ave. and Mowing NW CR 235

 

Work in the SW section consists of Grading SW 163rd St. and Picking up limbs on SW CR 225 an Patching troughs son SW CR 18

 

 

We received 3 Squads for a total of 11 people

 

1 Squad will be directing traffic for Picking up limbs on SW CR 225 and Filling in troughs on SW CR 18

 

1 Squad will be Picking up trash and Weed eating on SE 144th (Vystar Road) and SE CR 100A (Griffis Loop)

 

1 Squad will be Cleaning all County Parks