Tentative Work Schedule

 

August 28, 2018

 

Work in the NE section consists of Filling in pot holes on NE 162nd and in the Pizza hut/Annex parking lot and Trimming and Chipping trees around R/R tracks on NE 204th, NE 185th and Carter Road

 

Work in the NW section consists of Filling in holes on NW 188th Ter. and NW 105th, Pulling ditches on NW 212th, Digging a ditch off NW 53rd Ave. and Mowing NW 84th with the Side Arm 

 

Work in the SE section consists of Patching pot holes on SE 2nd Ave. (Keystone Golf and Country /Club), Mowing SE CR 100A, SE 144th (Vystar Road) and SE CR 230A and Mowing SE 21st Ave. with the Side Arm Mower

 

Work in the SW section consists of Sloping a ditch on SW CR 225A

 

 

We received 3 DOC Squads  for a total of 16 people

 

1 Squad will be patching pot holes in the Pizza Hut/Annex parking lot and SE 2nd Ave.

 

1 Squad will be trimming and chipping trees at R/R tracks on NE 204th, NE 185th and Carter Road

 

1 Squad will be directing traffic to slope a ditch at SW CR 225A