Tentative work schedule

September 30,2020

 

Work in the NE section consists of Grading NE 6th Lane and NE 20th Lane

 

Work in the NW section consists of Grading NW 246th St. Mow NW CR 225 and Patch Pot Holes on NW 177th St.

 

Work in the SE section consists of Packing the milling on SE 5th Ave.

 

Work in the SW section consists of Grading SW 180th, SW 114th and SW 180th Pl., Chipping on SW CR 225A, Trimming trees and Keeping debris off the road on SW CR 18 and Mowing SW CR 18

 

We received 2 DOC Squads for a total of 7 people

 

Both Squads will be helping with the Chipping on SW CR 225A