Work Schedule

 

Work in the NW section consists of Grading, Mowing, Cutting up trees and Trimming ROW, Patching pot holes and Installing Driveway Culvert

 

Work in the SE section consists of Grading and Patching pot holes

 

Work in the SW section consists of Building up road and fixing washouts and Cutting trees and Trimming ROW

 

 

We received 2 DOC Squads consisting of 12 people

 

1 Squad will be assisting in Cutting up trees & Trimming ROW in the NW section

 

1 Squad will be assisting with Traffic Control in the NW section installing a driveway culvert