Tentative Work Schedule

July 13, 2020

 

Work in the NE section consists of Mowing NE 20th Ave. and NE 17th Ave.

 

Work in the NW section consists of Grading NW 37th Ave. and Replacing a Crossover pipe on NW 59th Ave.

 

Work in the SE section consists of Mowing SE CR 100A

 

Work in the SW section consists of Prepping SW 104th Ave. and Grading SW 105th, SW 92nd and SW 147th

 

 

 

We received 1 DOC Squad for a total of 6 people

 

1 Squad will be Picking up trash and Weed eating on SW CR 18, SW CR 227 (Start at Fire Department), SW CR 225 and then SW CR 18 around Hampton Lake to 301

 

1 County Officer will be directing traffic for Replacing Crossover pipe on NW 59th Ave.