Tentative Work Schedule

March 19, 2019

 

Work in the NW section consists of Digging the ditch on NW 53rd Ave. and Patch driveways on NW 55th Ave.

 

Work in the SE section consists of digging ditches on SE 44th Ave.

 

Work in the SW section consists of Adding limerock & Grading SW 160th Ave., Grading SW 66th Ave. and Filling in troughs on SW CR 18

 

 

We received 3 DOC Squads for a total of 17 people

 

1 Squad will be Patching driveways on NW 55th Ave.

 

1 Squad will be Picking up trash and weed eating NW CR 225  (Revised)

 

1 Squad will be digging ditches on SE 44th Ave.