Tentative Work Schedule

November 1, 2018

 

Work in the NE section consists of Trimming and Chipping on NE 7th

 

Work in the NW section consists of Limerocking NW 75th Ave., Limerocking NW 228th, Scooping the ditch on NW 84th Ave. and Digging NW 53rd Ave. ditch

 

Work in the SE section consists of Mowing SE 50th (East of 21B) and SE 30th St.

 

Work in the SW section consists of Adding Clay and Enzymes and Zipping SW 101st Ave.

 

 

We received 3 DOC Squads for a total of 17 people

 

1 Squad will be patching a washed out culvert on SW 144th

 

1 Squad will be Trimming and Chipping on NE 7th

 

1 Squad will be directing traffic for Scooping ditches on NW 84th Ave.