Tentative Work Schedule

February 24, 2020

 

Work in the NW section consists of Grading off of NW CR 125 and Backfill a ditch on NW 53rd Ave

 

Work in the SE section consists of Patching a driveway at SE 43rd and SE 5th

 

Work in the SW section consists of Zipping and Prepping SW 101st Ave for Fog Sealing, Grading SW 132nd Ave., Mowing SW CR 231 from SR 18 to County Line

 

 

We received 3 DOC Squads for a total of 13 people

 

1 Squad will be Picking up trash and Weed eating SW CR 18 and SW CR 227

 

1 Squad will be Picking up trash and Weed eating SE 109th St.

 

1 Squad will be directing traffic for Prepping SW 101st Ave for Fog Sealing