Tentative Work Schedule

November 8, 2018

 

Work in the NE section consists of Pulling ditches on NE 171st St. then NE 12th & 173rd 

 

Work in the SE section consists of Installing a culvert on SE 129th St., Trimming and Chipping on SE 16th St. and Mow off of Immokalee Road, SE 35th, SE 2nd and then Crystal Lake Area

 

Work in the SW section consists of Zipping SW 101st, Grading SW 161st then Crosby Lake area, Install a culvert on SW 75th Ave and Mow SW CR 231 and SW CR 237

 

Work in the NW section consists of Patching pot holes on NW 84th Ave.

 

 

We received 3 DOC Squads for a total of 19 people

 

1 Squad will be picking up trash on Market Road, NE 173rd and all Boat Ramps

 

1 Squad will be Trimming and Chipping on SE 16th St.

 

1 Squad will be Patching Pot Holes on NW 84th Ave.