Tentative Work Schedule

January 22, 2019

 

Work in the NE section consists of Pulling ditches & Grade NE 204th St. & NE 20th Lane and Dig Ditches on NE 15th Ave. & NE 17th Ave.

 

Work in the NW section consists of Grading NW 212th and 74th, Finish Head Wall on NW 216th St. and Trim limbs on NW 233rd St.

 

Work in the SE section consists of Grading SE 73rd St.

 

 

We received 3 DOC Squads for a total of 15 people

 

1 Squad will be finishing Building a Head Wall on NW 216th St

 

1 Squad will be Picking up a couch, tires and pillows on SE 21st Ave. Picking up trash and weed eating on SW 75th Ave.

 

1 Squad will be Digging a ditch on NE 15th Ave. & NE 17th Ave.