Tentative Work Schedule

July 23, 2019

 

Work in the NE section consists of Digging and Cleaning the ditch on NE 227th St., Grading NE 247th, NE 227th and Carter Road and Mowing NE 247th

 

Work in the NW section consists of Grading the milled part of NW 177th St and NW 62nd Ave., Installing a culvert on NW CR 229 and Mowing NW 247th. NW 38th, NW CR 225 and NW CR 229

 

Work in the SE section consists of Mowing SE 73rd, SE 72nd, SE 71st, SE 4th, SE 5th, SE 7th and SE 66th and Patching a driveway on SE 73rd St. and SE 4th Ave

 

Work in the SW section consists of Mowing SW 75th Ave. and SW CR 100A 

 

 

We received 3 DOC Squads with a total of 14 people

 

1 Squad will be Picking up trash on SW CR 100A

 

1 Squad will be Picking up trash on SW 75th Ave. and SW CR 100A

 

1 Squad will be directing traffic for Installing a culvert on NW CR 229