Tentative Work Schedule

April 10, 2023

 

Work in the NE section consists on Moving the Paver and the Roller from NE 17th Ave. to Market Road pit

 

Work in the NW section consists of Grading all three (3) parts of NE 71st Ave., NW 41st Ave., NW 251st and NW 261st and Work on Beaver Dams on NW CR 200A, NW CR 125 and NW 216th 

 

Work in the SW section consists of Grading SW 92nd, SW 147th and SW 160th and Mowing SW CR 18, SW CR 225A and SW CR 104th