Tentative Work Schedule

 

 

Work in the NW section consists of Grading off of NW CR 125, Installing a culvert on NW 267th St. and Cleaning out a ditch on NW 53rd Ave.

 

Work in the SE section consists of Grading SE 57th St, SE 8th Ave. and off of SE CR 21B

 

Work in the SW section consists of Grading SW 132nd Ave and the Whitehead Settlement area, Patching pot holes on SW CR 235 and Mowing down SW CR 227 an SW CR 225

 

 

We received 3 DOC Squads for a total of 19 people

 

1 Squad will be Picking up trash and weed eating on SW CR 225

 

1 Squad will be Picking up trash and weed eating on SE CR 18

 

1 Squad will be directing traffic and patching pot holes on SW CR 235