Tentative Work Schedule

 

July 30, 2018

 

Work in the NE section consists of Digging Ditch on NE 14th Ave.

 

Work in the NW section consists of Building up the ditch on NW 41st Ave.

 

Work in the SE section consists of Digging Ditches in Lincoln City

 

Work in the SW section consists of Zipping SW 101st Ave. and Trim the trees at the intersection of SW CR 227 & SW CR 18

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be Patching and Building up driveways and placing concrete bags in ditch 

 

1 squad will be Trimming trees at the intersection of SW CR 227 & SW CR 18

 

1 Squad will be Patching pot holes on SE 21st Ave. and then SE 49th Ave. between Meng Dairy and the school