Tentative Work Schedule

December 12, 2018

 

Work in the NW section consists of Working materials into milling on NW 185th St., Grading NW 41st Ave., 44th Ave., 70th Ave., 71st Ave., & 74th Ave., Patching pot holes on NW 211th St. and County roads coming off of NW SR 16 intersections, Mow NW 71st, 193rd and 180th with the Side Arm Mower

 

Work in the SW section consists of Digging a ditch on Edwards Road

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be Patching pot holes on NW 211th St.

 

1 Squad will be Picking up trash and Weed eating NE 28th Ave. and NE 19th Ave.

 

1 Squad will be digging a ditch on Edwards Road