Tentative Work Schedule

February 6, 2019

 

Work in the NE section consists of Grading NE 173rd St & NE 12th Ave, Dig Ditch on NE 173rd St., Trim ROW on NE 24th Loop and Patch driveways at 17017 NE 19th Ave. and 18773 NE 223rd St.

 

Work in the NW section consists of Installing a culvert on NW 183rd St., Dig a ditch on NW CR 235 and Patch pot holes on NW CR 229A

 

Work in the SE section consists of Patching a driveway at 866 SE 40th Pl. and Grade Crystal Lake Homesite area

 

Work in the SW section consists of Grading SW 155th Ave.and Dig a ditch on SW 104th

 

 

We received 3 DOC Squads for a total of 19 people

 

1 Squad will be Picking  up Trash and Weed eating SE CR 18

 

1 Squad will be Patching pot holes and driveways

 

1 Squad will be directing traffic for Installing a culvert and Digging ditches