Tentative Work Schedule

November 26, 2018

 

Work in the NE section consists of Pulling ditches on NE 173rd St.

 

Work in the NW section Zipping NW 185th and Install a culvert on NW CR 235

 

Work in the SE section consists of Grading SE 49th Ave. and going towards Brooker off CR 18, Install a culvert at 866 SE 40th Pl., Patch pot holes and driveways on SE 66th St. and Mow SE 139th, 140th and 136th Loop with the Side Arm

 

 

We received 3 DOC Squads for a total of 19 people

 

1 Squad will be Patching Driveways and Pot Holes on SE 66th St.

 

1 Squad will be Picking up trash and Weed eating on SW CR 225 & SW CR 227

 

1 Squad will be directing traffic for installation of culverts on NW CR 235 and SE 40th Pl.