Tentative Work Schedule

November 5, 2019

 

Work in the NW section consists of Grading NW 196th St. (off 301) & NW 59th Ave., Cleaning out ditches on NW CR 235, Digging the Outfall Ditch on NW CR 225, Take down a tree on NW 236th St., Patch a hole at Water Oak Creek bridge on NW CR 225 and Mow NW 177th St an NW CR 233

 

Work in the SE section consists of Grading SE 11th Ave.

 

Work in the SW section consists of Cleaning out concrete ditch pavers on SW CR 231 (Dedan Loop) and Mowing SW CR 227 & SW CR 225

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be assisting with taking down a tree on NW 236th St. then assisting with traffic control and Patching a hole at Water Oak Creek bridge on NW CR 225

 

1 Squad will be Weed eating, picking up trash and cleaning out ditch pavers on SW CR 231 (Dedan Loop)

 

1 Squad will be directing traffic and assisting with Cleaning out ditches on SW CR 235