Tentative Work Schedule

March 1, 2022

 

Work in the NE section consists of Grading NE 171st St. and Mowing Paul Lane, NE 227th, NE 7th and NE236th

 

Work in the NW section consists of Grading NW 74th Ave., Cleaning out a Ditch on NW 178th Loop and Mow ROW NW 105th Ave. 

 

Work in the SW section consists of Grading SW 106th Ave. and SW 101st Ave., Work on the Bridge on SW CR 235A and Pick up trash on SW CR 235

 

 

We received 2 DOC (BCSO-JAIL) Officers and a total of 4 Inmates

 

1 Squad with 2 Inmates will be Picking up Trash and Weed Eating NW CR 229 and NW CR 220A

 

1 Squad with 2 Inmates will be Picking up Trash and Weed Eating on SE 109th St. and Picking up leaves on SE 38th Ave.